Mar 172009
 

Architect – Faulkner Browns

Services Engineers – Foremans / Acer Snowmec

Main Contractor – Laing O’Rourke

Mechanical Contractor – Crownhouse Technologies

xscape complete

The new £60m, 400,000 sq ft Xscape leisure facility, situated on the banks of the River Clyde at Braehead , Glasgow, is the third state of the art development of its kind in the United Kingdom.

With its unique, patented, real snow ski slopes Anderson Floor Warming are delighted to be part of a design teams, which has faced many challenges. The ski slope concrete structural slab contains our underfloor heating to protect the slab from frost heave. The snow layer on the ski slopes contains a matrix of our PEX pipe filled with chilled glycol to maintain the integrity of the snow layer.

xscape in progress

Products Used